Every formula in this topic, grouped by subtopic.

Work Rates & the LCM Method

One-day work
\frac{1}{T}
Combined time (two workers)
T = \frac{ab}{a + b}
Combined time (three workers)
T = \frac{abc}{ab + bc + ca}
Work done and left
\text{done} = \frac{t}{T}, \quad \text{left} = 1 - \frac{t}{T}

Efficiency, 'Twice as Good' & Ratio Cases

Efficiency and time
\frac{E_A}{E_B} = \frac{T_B}{T_A}
k-times worker
T_B = (k+1)T, \quad T_A = \frac{(k+1)T}{k}
Times from an efficiency ratio
E_A : E_B = a : b \Rightarrow T_A : T_B = b : a
Per cent more efficient
a\% \text{ more} \Rightarrow E_A : E_B = (100 + a) : 100

Pipes & Cisterns

Net speed
\text{net} = (\text{inlets}) - (\text{outlets})

Speeds in units per hour, with tank = LCM of the times.

Time to fill
T = \frac{\text{capacity}}{\text{net speed}}
Two inlets
T = \frac{a b}{a + b}

Both pipes fill.

One inlet, one outlet
T = \frac{a b}{b - a}

a = filling time, b = emptying time, b > a.

Leak time from two fill times
T_{\text{leak}} = \frac{t_1 t_2}{t_2 - t_1}

t₁ = normal time, t₂ = time with the leak.

Stage method
t_2 = \frac{\text{capacity} - \text{speed}_1 \times t_1}{\text{speed}_2}

Men–Days–Hours Chain & Provisions

MDH chain
M_1 D_1 H_1 E_1 = M_2 D_2 H_2 E_2 \quad (W_1 = W_2)
Men and days constant
M_1 D_1 = M_2 D_2
Provisions remaining
\text{days} = \frac{M_1 (D_{total} - t)}{M_2}
Work scaling
W_2 = W_1 \times \frac{M_2}{M_1} \times \frac{D_2}{D_1}

Joining / Leaving Mid-work, Alternate Days & Wages

Work done by A in t days
\frac{t}{T_A}
Leaves t days before the end
\frac{T - t}{T_A} + \frac{T}{T_B} = 1
Two-day cycle
\frac{1}{T_A} + \frac{1}{T_B} \text{ per 2 days}
Wage split
w_A = \text{total} \times \frac{1/T_A}{1/T_A + 1/T_B}

How these Time & Work formulas are used

The cards above hold 22 formulas across 5 subtopics: Work Rates & the LCM Method (4), Efficiency, 'Twice as Good' & Ratio Cases (4), Pipes & Cisterns (6), Men–Days–Hours Chain & Provisions (4) and Joining / Leaving Mid-work, Alternate Days & Wages (4). Of the 28 recurring question types catalogued for this topic, 25 are solved directly from a formula; the rest need a method or a table rather than a single relation. A formula sheet only helps when you know which words in a question call for which formula, so the section below pairs each subtopic with the question types that use its formulas, a worked case taken from the lessons, and a note on when to apply it.

Jump to: Work Rates & the LCM Method · Efficiency, 'Twice as Good' & Ratio Cases · Pipes & Cisterns · Men–Days–Hours Chain & Provisions · Joining / Leaving Mid-work, Alternate Days & Wages

Formulas in action

For each subtopic: what it deals with, when the formula applies, and a worked example from our lessons.

Work Rates & the LCM Method

4 formulas on this page

Treat one whole job as the unit of work. A worker who finishes it in T days has a rate of \dfrac{1}{T} per day, and rates add when people work together.

Two workers together (or the reverse) · asked very common

Use it when: Two individual times are given and the together time is asked — or the together time and one person's time are given and the other person is asked.

T = \frac{ab}{a + b}, \qquad \frac{1}{T_B} = \frac{1}{T_{A+B}} - \frac{1}{T_A}
Worked example

A finishes a job in 15 days and B in 10 days. Working together, in how many days do they finish it?

  1. Job = LCM(15, 10) = 3030 units.

  2. A: 30÷15=230 \div 15 = 2/day; B: 30÷10=330 \div 10 = 3/day.

  3. Together 55/day → 30÷5=630 \div 5 = 6 days.

Answer:

6 days

Three or more workers together · asked very common

Use it when: Three individual times are given (or two times plus the trio time) and the combined time — or one missing individual time — is asked.

\frac{1}{T} = \frac{1}{T_A} + \frac{1}{T_B} + \frac{1}{T_C}, \qquad T = \frac{abc}{ab + bc + ca}
Worked example

A, B and C can do a piece of work in 9, 12 and 18 days respectively. In how many days will they finish it together?

  1. Job = LCM(9, 12, 18) = 3636 units.

  2. Rates: 4+3+2=94 + 3 + 2 = 9 a day.

  3. 36÷9=436 \div 9 = 4 days.

Answer:

4 days

Full lesson: Work Rates & the LCM Method →

Efficiency, 'Twice as Good' & Ratio Cases

4 formulas on this page

Efficiency is rate: the share of a job a person finishes per day. Efficiency and time are inversely proportional — twice as efficient means half the days.

'k times as efficient', together time given · asked very common

Use it when: 'A is twice/thrice as efficient as B and together they finish in T days' — the individual times are asked.

T_B = (k+1)T, \qquad T_A = \frac{(k+1)T}{k}
Worked example

A is twice as efficient as B and together they complete a work in 18 days. B alone can complete it in:

  1. Rates: A =2= 2, B =1= 1 → 33/day.

  2. Job =3×18=54= 3 \times 18 = 54 units.

  3. B alone =54÷1=54= 54 \div 1 = 54 days (A alone 2727).

Answer:

54 days

Efficiency ratio given as a : b · asked common

Use it when: An explicit ratio like 3 : 2 is given for the efficiencies, with either the together time or one person's time.

\text{job} = (a + b) \times T \text{ units}, \qquad T_{\text{weak}} = \frac{(a+b)T}{b}
Worked example

The efficiencies of A and B are in the ratio 3 : 2. B alone can finish the work in 30 days. Working together, they will finish it in:

  1. B: 2u=1302u = \dfrac{1}{30} → u=160u = \dfrac{1}{60}.

  2. Together 5u=560=1125u = \dfrac{5}{60} = \dfrac{1}{12} per day.

  3. 1212 days.

Answer:

12 days

Full lesson: Efficiency, 'Twice as Good' & Ratio Cases →

Pipes & Cisterns

6 formulas on this page

A tank is filled by some pipes and emptied by others. A pipe that fills is an *inlet*. A pipe or a leak that empties is an *outlet*.

Two or three filling pipes together · asked very common

Use it when: All the pipes fill the same tank. Each pipe's time is given, and the time with all of them open is asked.

\frac{1}{T} = \frac{1}{T_1} + \frac{1}{T_2} + \frac{1}{T_3}
Worked example

Three pipes can fill a tank in 20, 30 and 60 minutes. If all three are opened together, the tank fills in:

  1. Tank = LCM(20, 30, 60) = 60 units.

  2. Speeds: 3, 2 and 1 units per minute.

  3. Total speed = 6 units per minute.

  4. Time = 60÷6=1060 \div 6 = 10 minutes.

Answer:

10 minutes

Filling and emptying pipes open together · asked very common

Use it when: At least one pipe fills and at least one pipe (or a leak) empties, all at the same time.

\text{net} = \sum \text{inlets} - \sum \text{outlets}
Worked example

Pipes A and B fill a tank in 12 hours and 15 hours. Pipe C empties it in 20 hours. If all three are opened together, the tank fills in:

  1. Tank = LCM(12, 15, 20) = 60 units.

  2. A = +5, B = +4, C = −3.

  3. Net speed = 6 units per hour.

  4. Time = 60÷6=1060 \div 6 = 10 hours.

Answer:

10 hours

Full lesson: Pipes & Cisterns →

Men–Days–Hours Chain & Provisions

4 formulas on this page

Total work is the product of the resources: W = M \times D \times H \times E — men, days, hours per day, efficiency.

Men–days–hours chain · asked very common

Use it when: One scenario of men, days and (maybe) hours per day is given; a second scenario changes some of them and one value is asked.

M_1 D_1 H_1 E_1 = M_2 D_2 H_2 E_2
Worked example

If 12 men working 8 hours a day can complete a work in 15 days, in how many days will 18 men working 10 hours a day complete it?

  1. Work =12×15×8=1440= 12 \times 15 \times 8 = 1440 man-hours.

  2. New crew supplies 18×10=18018 \times 10 = 180 man-hours a day.

  3. 1440÷180=81440 \div 180 = 8 days.

Answer:

8 days

Provisions of a garrison / hostel · asked very common

Use it when: Food or fodder for M men for D days; after t days some men join or leave; how much longer the stock lasts is asked.

\text{days} = \frac{M_1 (D - t)}{M_2}
Worked example

A garrison of 400 men has provisions for 25 days. After 5 days, 100 more men join. The provisions will now last:

  1. Stock left =400×(25−5)=8000= 400 \times (25 - 5) = 8000 man-days.

  2. New headcount =500= 500.

  3. 8000÷500=168000 \div 500 = 16 days.

Answer:

16 days

Full lesson: Men–Days–Hours Chain & Provisions →

Joining / Leaving Mid-work, Alternate Days & Wages

4 formulas on this page

Every twist here — leaving, joining, alternating, wages — uses one method: count the work each person actually did.

A leaves after t days · asked very common

Use it when: A works a few days and leaves; B (or B and C, or the rest of the team) completes the remaining work; the remaining or total days are asked.

\text{remaining work} = 1 - \frac{t}{T_A}, \qquad \text{days} = \frac{\text{remaining}}{\text{continuing rate}}
Worked example

A can do a work in 12 days and B in 18 days. A works for 3 days and then leaves. In how many days will B alone finish the remaining work?

  1. A does 312=14\dfrac{3}{12} = \dfrac{1}{4}.

  2. Remaining =34= \dfrac{3}{4}.

  3. B needs 34×18=13.5\dfrac{3}{4} \times 18 = 13.5 days.

Answer:

13.5 days

Wages split by work done · asked very common

Use it when: A total wage for a joint job is given; find one person's share — sometimes with unequal days worked or an unknown member.

w_A : w_B = (\text{rate}_A \times d_A) : (\text{rate}_B \times d_B)
Worked example

A and B together earn ₹600 for a job. A alone can do the job in 10 days and B alone in 15 days. A's share is:

  1. Job =30= 30 units: rates 3:23 : 2.

  2. A gets 35×600=₹360\dfrac{3}{5} \times 600 = ₹360 (B: ₹240₹240).

Answer:

₹360

Full lesson: Joining / Leaving Mid-work, Alternate Days & Wages →

Common mistakes when applying Time & Work formulas

Knowing a formula and applying it correctly are different skills. These are the slips flagged in the lessons.

  • Work Rates & the LCM Method

    Common slip: Adding the days (12 + 24 = 36) instead of adding the rates.

    Instead: Rates add, days do not. The together time is ab/(a+b), and it must be less than the smaller time.

  • Efficiency, 'Twice as Good' & Ratio Cases

    Common slip: Reading 'twice as efficient' as twice the days.

    Instead: Efficiency up means days down — half the days, not double.

  • Pipes & Cisterns

    Common slip: Adding the emptying pipe's speed as if it fills the tank.

    Instead: Put a minus sign in front of every outlet or leak before adding.

  • Men–Days–Hours Chain & Provisions

    Common slip: Writing more men on the wrong side (more men, more days).

    Instead: For a fixed job men and days are inverse: M₁D₁ = M₂D₂.

  • Joining / Leaving Mid-work, Alternate Days & Wages

    Common slip: Splitting wages by days alone when efficiencies differ.

    Instead: Wages follow work done: rate × days for each person.

  • Work Rates & the LCM Method

    Common slip: For three workers, applying ab/(a+b) to a pair and merging again.

    Instead: Add all three rates in one line, or use abc/(ab+bc+ca).

  • Efficiency, 'Twice as Good' & Ratio Cases

    Common slip: Giving the k-times worker (k+1)T days.

    Instead: That is the weaker worker's time. The stronger takes (k+1)T/k.

  • Pipes & Cisterns

    Common slip: Using \dfrac{ab}{a+b} for one filling and one emptying pipe.

    Instead: That formula is for two inlets. For fill + empty use \dfrac{ab}{b-a}.

How to memorise this sheet

Cover the right-hand side of each formula and reproduce it from its name, then check. A formula you can only recognise on the page will not come back under exam pressure. For each one, also say aloud which words in a question should make you reach for it.

With 22 formulas, do not try to learn them in one sitting. Take one subtopic at a time, test yourself the next day, then again after a few days; the revision planner can schedule those repeats.

Put them to use: read the lessons, work through the 5 solved examples and then take the 61-question practice test. The combined sheet for every topic is on the all-topics formula sheet.